December Tram Diaries - Big Red is Back! 01.01.09
We did it. Or, should I say, they did it!
Read more...
|
|
November Tram Diaries - Testing the Tram 12.01.08
With the close of November came the
opening of Jackson Hole Mountain Resort. Teewinot and Après Vous opened on
Saturday with about 70 inches of snow on Rendezvous Mountain.
Read more...
|
|
October Tram Diaries - Cars Go Up! 11.01.08
Snow continues to fall here in Jackson Hole, blanketing the new five
towers, the new upper and lower terminals and the new tram cars,
hanging from steel cables.
Read more...
|
|
September Tram Diaries - Almost Ready 10.01.08
From south of town, the new upper tram terminal is visible. As you
drive north into Jackson, the towers – catching the sunlight – come
into view.
Read more...
|
|
August Tram Diaries - Cables Climb Skyward 09.01.08
From the catwalk of the upper terminal, the newly tensioned tram cables
look like tight ropes you could walk on all the way to the clock tower.
Read more...
|
|
July Tram Diaries - The Countdown Is On! 08.01.08
Glistening with new fire engine red paint, the two new tram cars sit in a warehouse in Olten, Switzerland awaiting inspection.
Read more...
|
|
June Tram Diaries - Early Summer Construction 07.01.08
The big news this month is the promotion of Tim Mason to Vice President of Operations. In his new position, Mason will oversee all areas of on-mountain operations, including lifts, ski patrol, grooming, mountain facilities, parking as well as summer operations.
Read more...
|
|
May Tram Diaries Part 2 - Road Work 05.15.08
The welcomed precipitation that granted soft landings for epic hucks and powder skiing into May has once again slowed construction of the new aerial tram.
Read more...
|
|
May Tram Diaries Part 1 - Towers Come Down, Go Up 05.01.08
It’s officially spring in Jackson Hole, but for the past month and a
half work crews assembling the new red box under wintry conditions. In
fact, it took nearly three weeks just to clear snow off the mountain
road.
Read more...
|
|
March/April Tram Diaries - Record Winter, Spring Construction 04.01.08
Well, the end of an epic season has come and gone and now the real work begins.
Read more...
|
|
Feb/March Tram Diaries - Base Pours 03.01.08
Besides surpassing 500 - and then 600 - inches of snow this season, during February and March “It was mainly all bottom terminal,” said Tim Mason, interim operations
manager for the resort. “They poured the North wall and then the South
wall.”
Read more...
|
|
January Tram Diaries - Switzerland Trip 01.01.08
Winds howled, snow accumulated and construction at Jackson Hole
Mountain Resort seemed quiet during January. Within the canvas and
steel tent at the site of the new bottom terminal, crews from Las
Vegas’ Gunderson poured 484 yards of concrete into what will become the
foundation and floor.
Read more...
|
|
December Tram Diaries - Snowy Base Construction 12.01.07
Tim Mason, who runs Mountain Operations for the resort said the most
exciting moment of the month came when 15 inches of new snow fell. Both
Mason and General Manager Tom Spangler agreed that December was a
slow-moving month for construction and that people were mostly
concentrated on skiing.
Read more...
|
|
November Tram Diaries - Bottom Terminal and Tower 1 11.01.07
Besides a little bit of patchwork on some towers to fill in some holes
in the concrete, all the focus was the lower terminal in November.
Read more...
|
|
October Tram Diaries - The Month of Concrete 10.01.07
October was a mixture of concrete and snow for crews working on dismantling old buildings and pouring new foundations. Crews completed pouring concrete for the counterweight "house" on top of Rendezvous Mountain during the month. They also finished pouring the
concrete pads on the upper terminal that support the walkway for
disembarking tram passengers as well as the bollard foundations.
Read more...
|
|
September Tram Diaries - Clocktower Removal 09.01.07
People turned their grief of losing the iconic 82-foot clock tower
steeple at the base of Teton Village into opportunity this month. They
sawed the clock's hands and removed numbers for mementos of the old
tram's era the night before demolition started.
Read more...
|
|
August Tram Diaries - A Little History 08.01.07
Welcome to Jackson Hole’s Tram Diaries, a monthly update on the construction of the new 100-passenger aerial tram, opening December 2008.
Read more...
|
| Press Releases |
|
Jackson Hole Aerial Tram Ready to Fly! 10.29.08
It's a historic day in Jackson Hole as Tram Car #1 is placed on the track cables.
Read more...
|
|
Terminal Design for New Tram Unveiled 02.23.07
A clock tower will remain as a landmark for Teton Village, as JHMR
Board Members recently approved the design that included this
feature as part of the lower terminal of the new Aerial Tram at Jackson
Hole Mountain Resort.
Read more...
|
|
New Tram Announcement 08.09.06
Jackson Hole Mountain Resort
(JHMR) officials announced today their intention to enhance the legacy
created over the last 40 years by committing to build a new 100
passenger, state of the art aerial tramway from the base in Teton
Village to the summit of Rendezvous Mountain, a vertical rise of
4,139'. This lift will have the longest continual vertical rise of any
ski lift in North America. It will replace the existing smaller aerial
tram that will cease to operate October 1, 2006.
Read more...
|
|
Tram Replacement Options Narrow 02.01.06 The June 2005 decision to close
the Aerial Tram October 2006 was made following 18 months of
unprecedented evaluation into all facets of Tram operations by leading
industry engineers. The results required JHMR to make a decision
regarding ongoing tram operations. Although tough and emotional news,
JHMR is now focusing its attention on the future and feasible solutions
regarding tram replacement.
Read more...
|
|
The Tram - Our Perspective 01.14.06 Since June 24th when Jackson Hole Mountain Resort (JHMR) made our
announcement regarding the Tram there has been untold emotion, ideas,
discussion, and speculation about the next steps. This response was
certainly expected given the importance of the Tram in our community,
to our guests and to our economy.
Read more...
|
|
Jackson Hole Tram - Local News Articles 06.25.05 A state program designed to
promote economic development could potentially provide financial
assistance for construction of a new tram, Governor Freudenthal said
Wednesday.
Read more...
|
|
After 40 Years of Service, JHMR Aerial Tram Will Be Retired End of Summer ‘06 06.24.05 Jackson Hole’s Aerial Tram in Teton Village will be retired at the end
of the 2006 summer season after 40 years of tireless service, Jackson
Hole Mountain Resort officials announced today.
Read more...
|